Summary
Case submitted by: Heijmans Infra Techniek
Country: The Netherlands
Built-up site?: Yes
Soil type: Layered soil clay/peat/sand
In-situ remediation technique: In situ chemical Reduction (ISCR)
Follow-up required?: Monitoring
Treated contamination: Chlorinated Volatile Organic Compounds (CVOC)
Medium contamination: Soil/pure product and groundwater
Dimension contamination: 8000 m3
Remediation goal: Control
Remediation goal achieved?: No, there is still water extraction and the site is still being monitored
Initial and final concentration or load removal:
Tetrachloro-ethene initial concentration: 10000 ug/l
Trichlooretheen initial concentration: 10000 ug/l
Active remediation phase: Applied in 2001, started in 2005 untill 2008
Passive remediation phase: The passive remediation phase is not yet completed. Expected realization period: 2008 untill unknown. Permanent control required.
Added reports:
Amersfoort Eindrapport
In situ Chemische Reductie (ISCR)
Case detailed information
General information
Project name: Amersfoort: CVOC***
Case submitted by: Heijmans Infra Techniek
Contact: Dhr. A. Peene
Address: Postbus 68 / 5240 AB Rosmalen
Telephone number: +31 (0)73 543 68 01
Email-address: apeene@heijmans.nl
Location
Country: The Netherlands
City/region/county: Amersfoort, Utrecht
(future) use of location: Residential
Built-up location during the active remediation phase?: Yes
Technique
Explanation technique: Funnel & Gate
Also other remediation techniques applied?: No
After care needed?: Monitoring
Rationale for the chosen technique: Control in urban areas, surface treatment undesirable and extensive care is needed.
Contamination
Treated contaminant(s): Chlorinated Volatile Organic Compounds (CVOC)
Contaminant phase: Soil/pure product and groundwater
Size contamination: 8000 m3
Depth contamination: 13 m below surface
Soil
Soil type: Layered soil clay/peat/sand
Saturated/unsaturated zone?: Saturated zone
Permeability: 0,01-0,1 m/day
Flow velocity or gradient groundwater:
Result, duration, expense
Remediation goal: Control
Remediation goal achieved?: No, there is still water extraction and the site is still being monitored
Initial and final concentration and load removal:
Tetrachloro-ethene initial concentration: 10000 ug/l
Trichlooretheen initial concentration: 10000 ug/l
Active remediation phase: Applied in 2001, started in 2005 untill 2008
Passive remediation phase: The passive remediation phase is not yet completed. Expected realization period: 2008 untill unknown. Permanent control required.
Total costs passive/after care phase: € 1500.000,-
Total costs active phase: € 1.000.000,-
Stakeholders
Problem owner: CSG Eemkwartier
Contractor: Heijmans Infra Techniek
Remediation plan: Heijmans Milieutechniek (Now: Heijmans Infra Techniek)
Remediation research:
Competent authority: Provincie Utrecht
Contact information stake holders:
Additional information
Lessons learned: Working in a closed system with a free-fall below the groundwaterlevel is very sensitive.
Remarks: