Summary

Case submitted by: NTP Milieu
Country: The Netherlands
Built-up site?: Yes, the construction was being dismantled.
Soil type: Layered soil; clay/peat/sand
Follow-up required?: No
Treated contamination: CVOC
Medium contamination: Groundwater
Dimension contamination: 45.000 [m3]
Remediation goal:
Final concentration
PCE concentration: 20 µg/l
TCE concentration: 262 µg/l
Cis concentration: 10 µg/l
VC concentration: 2,5 µg/l
Load removal percentage: > 95%
Remediation goal achieved?: yes
Initial and final concentration or load removal:
Cis initial concentration: 1.700 µg/l; final concentration: < 10 µg/l
VC initial concentration: 700 µg/l; final concentration: 2,5 µg/l
Active remediation phase: Mei 2005 until juni 2006
Passive remediation phase:

Case detailed information

General information
Project name: Boekelo (Texoprint): CVOC *** Case submitted by: NTP Milieu Contact: De heer J.M. Wiggers Address: Postbus 6280, 7503 GG Enschede Telephone number: +31(0)53 4614905 Email-address: h.wiggers@ntp-enschede.nl
Location
Country: The Netherlands City/region/county: Texoprint Boekelo, provincie Overijssel (future) use of location: Living Built-up location during the active remediation phase?: Yes, the construction was being dismantled.
Technique
Explanation technique: Also other remediation techniques applied?: Yes, namely: Excavation of other partial locations with several soil contermanations and dismantle en removal of several silt basin. After care needed?: No Rationale for the chosen technique: Stimulated aerobic degradation is the best option for the degradation of CVOC (Cis and VC) in groundwater in a built-up site. Groundwater remediation through groundwater circulation and air sparging.
Contamination
Treated contaminant(s): CVOC Contaminant phase: Groundwater Size contamination: 45.000 [m3] Depth contamination: 11 m below surface
Soil
Soil type: Layered soil; clay/peat/sand Saturated/unsaturated zone?: Saturated zone Permeability: > 0,1 m/day Flow velocity or gradient groundwater: 1,1 m/km; 10 m/year
Result, duration, expense
Remediation goal: Final concentration PCE concentration: 20 µg/l TCE concentration: 262 µg/l Cis concentration: 10 µg/l VC concentration: 2,5 µg/l Load removal percentage: > 95% Remediation goal achieved?: yes Initial and final concentration and load removal: Cis initial concentration: 1.700 µg/l; final concentration: < 10 µg/l VC initial concentration: 700 µg/l; final concentration: 2,5 µg/l Active remediation phase: Mei 2005 until juni 2006 Passive remediation phase: Total costs passive/after care phase: Total costs active phase: € 105.000 ,-
Stakeholders
Problem owner: Ter Steege Vastgoed BV Contractor: NTP Milieu Enschede Remediation plan: NTP Milieu Enschede Remediation research: Grontmij Competent authority: Gemeente Enschede Contact information stake holders: De heer H. Wiggers NTP Milieu
Additional information
Lessons learned: No remarks, groundwater remediation was successful Remarks: